2021 Albany Capital Improvements

Date: April-August 2021

Location: Albany, MN

Owner: City of Albany

Engineer: Stantec 

​

​

Craig Bardson Excavating excavated and hauled out 11,000 cubic yards of bad clay beneath 7 blocks of city streets and imported 12,000 tons of clean sand to bring the streets back to grade.  Clearing and grubbing, asphalt reclamation, removals, class 5 placement, topsoil placement, fabric and drain tile installation were also part of the subcontract. 

​

​